Give me example to calculate project cost with inflation in data sets in stackby.
You can use the following formula:
- Cost: The initial or current cost of the project.
- Inflation Rate: The annual rate of inflation (expressed as a decimal). For example, if the inflation rate is 5%, enter it as 0.05.
- Years: The number of years you expect the project to last or the period over which inflation will affect the cost.
How to Use in Stackby:
- Set Up Your Columns:
- Create a column for Cost (e.g., $10,000).
- Create a column for Inflation Rate (e.g., 0.04 for 4%).
- Create a column for Years (e.g., 5).
- Apply the Formula:
- Use the formula in Stackby as: POWER( (1+{Inflation rate}), {Years})*Cost
- Example Calculation:
- If your project cost is $10,000, the inflation rate is 4% (0.04), and the project spans 5 years:
- The project cost after 5 years will be approximately $12,167.